Concrete Yardage Chart: Slab Volume, Bags, and Truck Loads
A slab volume chart in cubic yards and 60 lb / 80 lb bags by size and thickness, plus how to order ready-mix, what to add for waste, and where short loads cost extra.
By BuildCalc · Published October 2, 2026 · 7 min read
Cubic yards of concrete equal length times width times thickness, all in feet, divided by 27. A 10 ft by 10 ft slab that is 4 inches thick holds 33.33 cubic feet, which is 1.23 cubic yards. Ready-mix plants sell by the cubic yard, so that is the number to start from.
Every volume, bag count, and truck figure in the tables comes from the same engine as the concrete slab calculator. Where a table shows a waste figure, it uses 10%.
The yardage formula
Convert every dimension to feet before multiplying. Thickness is the one that gets missed: 4 inches is 4 ÷ 12 = 0.333 ft, not 4. Then divide the result by 27, the number of cubic feet in a cubic yard (3 × 3 × 3).
Multiplying 27 by 12 gives a shortcut that works at any slab size: one cubic yard covers 324 ÷ thickness (in inches) square feet. At 4 inches that is 81 sq ft, and at 6 inches it is 54 sq ft. If your result is far from those figures, a conversion went wrong.
Slab volume chart
| Slab size | Area (sq ft) | 4 in. | 5 in. | 6 in. |
|---|---|---|---|---|
| 10 x 10 ft | 100 | 1.23 | 1.54 | 1.85 |
| 12 x 12 ft | 144 | 1.78 | 2.22 | 2.67 |
| 12 x 20 ft | 240 | 2.96 | 3.70 | 4.44 |
| 20 x 20 ft | 400 | 4.94 | 6.17 | 7.41 |
| 20 x 24 ft | 480 | 5.93 | 7.41 | 8.89 |
| 24 x 24 ft | 576 | 7.11 | 8.89 | 10.67 |
| 24 x 30 ft | 720 | 8.89 | 11.11 | 13.33 |
| 30 x 40 ft | 1,200 | 14.81 | 18.52 | 22.22 |
Multiply by 1.10 for a 10% ordering allowance.
Volume grows in direct proportion to both area and thickness, so the chart can be extended without another table. The 5-inch column is always 1.25 times the 4-inch column, and the 6-inch column is 1.5 times it. Two 20 x 20 ft slabs at 4 inches need 2 × 4.94 = 9.88 cubic yards.
For an L-shaped or otherwise irregular slab, split the plan into rectangles, look up or calculate each one, and add the results. Subtract openings only when they are large and fully formed out, such as a floor penetration or a sump pit. Small blockouts for posts rarely change the order by a measurable amount.
Thickness conversions
| Thickness (in.) | Decimal feet | ft³ per 100 sq ft | yd³ per 100 sq ft | sq ft per yd³ |
|---|---|---|---|---|
| 2 | 0.167 | 16.67 | 0.62 | 162.0 |
| 3 | 0.250 | 25.00 | 0.93 | 108.0 |
| 3.5 | 0.292 | 29.17 | 1.08 | 92.6 |
| 4 | 0.333 | 33.33 | 1.23 | 81.0 |
| 5 | 0.417 | 41.67 | 1.54 | 64.8 |
| 6 | 0.500 | 50.00 | 1.85 | 54.0 |
| 8 | 0.667 | 66.67 | 2.47 | 40.5 |
| 10 | 0.833 | 83.33 | 3.09 | 32.4 |
| 12 | 1.000 | 100.00 | 3.70 | 27.0 |
Lumber sizes cause more thickness errors than arithmetic does. A nominal 2 x 4 laid on edge is 3.5 inches tall, and a 2 x 6 is 5.5 inches tall. A slab screeded to the top of 2 x 4 forms over a level subgrade is 3.5 inches thick, which is the IRC R506.1 minimum for slab-on-ground floors. Local amendments can change that minimum.
The difference matters for the order. A 3.5-inch slab needs 1.08 cubic yards per 100 sq ft. A 4-inch slab needs 1.23, which is 14% more. Pick the design thickness first, then choose form lumber that produces it, and price the order from the thickness you will actually form.
Bag counts for 60 lb and 80 lb mixes
Bag labels list a yield: about 0.45 cubic feet for a 60 lb bag and about 0.60 cubic feet for an 80 lb bag. The calculator uses those two figures. Yields differ slightly between brands, so read the label on the product you buy.
One cubic yard is 27 cubic feet. That takes 60 bags of 60 lb or 45 bags of 80 lb, which is 3,600 lb of dry mix either way.
| Job | Volume (ft³) | 60 lb net | 80 lb net | 60 lb +10% | 80 lb +10% |
|---|---|---|---|---|---|
| 4 x 4 ft landing, 4 in. | 5.3 | 12 | 9 | 14 | 10 |
| 4 x 8 ft pad, 4 in. | 10.7 | 24 | 18 | 27 | 20 |
| 10 x 10 ft patio, 4 in. | 33.3 | 75 | 56 | 82 | 62 |
| 12 x 12 ft patio, 4 in. | 48.0 | 107 | 80 | 118 | 88 |
| 12 x 20 ft pad, 4 in. | 80.0 | 178 | 134 | 196 | 147 |
Bag counts round up to whole bags. Each column rounds separately.
Bags suit repairs, post holes, steps, and small pads. On a slab of several yards, hand mixing stops being practical. A 20 x 24 ft slab at 5 inches needs 334 bags of 80 lb, or 26,720 lb of dry mix, and mixing that many batches takes hours. The first batch can start to set before the last one is placed, which can leave visible seams and cold joints.
Footings and round piers
The calculator treats a footing as a rectangular prism: length times width times depth. A 100 ft run of footing 16 inches wide and 8 inches deep is 100 × 1.333 × 0.667 = 88.89 cubic feet, or 3.29 cubic yards.
| Footing width | 8 in. deep | 10 in. deep | 12 in. deep |
|---|---|---|---|
| 12 in. wide | 2.47 | 3.09 | 3.70 |
| 16 in. wide | 3.29 | 4.12 | 4.94 |
| 20 in. wide | 4.12 | 5.14 | 6.17 |
| 24 in. wide | 4.94 | 6.17 | 7.41 |
Step-downs, thickened slab edges, and pad sections at columns are separate prisms. Calculate each one and add it to the run. A footing poured into an unformed trench takes the shape of the trench, and sandy or soft soil sloughs into it. Measure the finished trench width and depth at several points, and use the averages instead of the drawn dimensions.
A round pier is a cylinder: π × (diameter ÷ 2)² × depth. A 12-inch pier is 1 ft across, so a 4 ft deep pier holds π × 0.5² × 4 = 3.14 cubic feet. The engine reads the pier depth from its length field.
| Diameter | 60 lb bags, 1 pier | 80 lb bags, 1 pier | yd³, 10 piers |
|---|---|---|---|
| 8 in. | 4 | 3 | 0.52 |
| 10 in. | 5 | 4 | 0.81 |
| 12 in. | 7 | 6 | 1.16 |
| 16 in. | 13 | 10 | 2.07 |
| 18 in. | 16 | 12 | 2.62 |
| 24 in. | 28 | 21 | 4.65 |
Bag counts are net and round up. Use the measured hole diameter when the soil is loose or the form tube is pulled.
Worked example: 20 x 24 ft slab, 5 inches thick
- Area: 20 × 24 = 480 sq ft.
- Volume: 480 × 5 ÷ 12 = 200 cubic feet.
- Net cubic yards: 200 ÷ 27 = 7.41.
- Add 10%: 7.41 × 1.10 = 8.15 cubic yards to order.
- Trucks: 8.15 cubic yards fits in 1 load at the 10 cubic yard planning capacity.
Ten percent of a 5-inch slab is half an inch of average extra depth. It is a margin for normal subgrade variation. It does not cover a systematic error. Suppose grading leaves the subgrade 3/4 inch low on average, so the slab averages 5.75 inches. The volume becomes 480 × 5.75 ÷ 12 ÷ 27 = 8.52 cubic yards, which is 0.37 cubic yards more than the 8.15 ordered. Each quarter inch of average depth over 480 sq ft is 10 cubic feet, or 0.37 cubic yards.
Ordering ready-mix
Give the plant the volume in cubic yards, the compressive strength from the plans or local code, the slump you want, the maximum aggregate size, and whether the concrete needs air entrainment for freeze-thaw exposure. Add the placement method (chute, wheelbarrow, or pump), the site address, and a delivery window.
The calculator assumes a mixer truck holds 10 cubic yards. That is a planning figure. Actual capacity depends on the truck and on local weight limits, so ask the plant what it will send. A full 10 cubic yard load weighs about 40,500 lb at 4,050 lb per cubic yard, so check the route across any driveway, septic lid, or culvert before the truck arrives.
Many plants charge an extra fee when an order, or the last load of an order, falls below a set quantity. The threshold and the fee differ from plant to plant. Ask for both before you settle on a number, because a small change in the order can move it across the threshold.
Time matters once the truck is loaded. ASTM C94 sets a default limit of 1.5 hours or 300 drum revolutions after batching, whichever comes first, unless the buyer and the supplier agree otherwise. Have the forms, reinforcement, and finishing crew ready before the truck leaves the plant. See the material waste guide for how allowances compare across materials, and the rebar weight chart for reinforcement quantities.
Why pours run over or short
- Low subgrade. Over-excavated spots, wheel ruts, and fill that settles all add depth. An average of half an inch extra uses the whole 10% allowance on a 5-inch slab. Fill low spots with compacted base, not concrete.
- Nominal lumber. Forms made from 2 x 4s give 3.5 inches, not 4. Forms that bow outward under the weight of wet concrete add volume along their whole length. Stake and brace them so the formed depth matches the order.
- Rain before the pour. Standing water in the forms must be removed, and a saturated subgrade ruts under wheelbarrows and washes at the edges. Re-grade and re-compact softened areas, then re-measure depth before you confirm the quantity. Rain during a pour shortens the usable window, so check the C94 time limit above.
- Water added to fix slump. Water raises slump, but it does not make more useful concrete. It lowers strength and raises shrinkage cracking. If the mix is too stiff to place, ask the plant about a water-reducing admixture.
- A missing division. Forgetting the ÷ 12 on thickness makes a slab look 12 times too large, and forgetting ÷ 27 makes it look 27 times too large. Check the result against the 324 ÷ thickness shortcut.
- Ordering exactly the net volume. Concrete cannot be added later once the last truck is gone. A late top-up load leaves a cold joint. Order a margin, and plan a use for leftover concrete, such as a small pad or stepping stones in a form set aside for that purpose.
Reinforcement, control joints, and sub-base thickness change the design and sometimes the volume. Follow the plans and the engineer of record, and check the calculator again whenever the formed dimensions change.
Frequently asked questions
How many cubic yards of concrete do I need for a 10 x 10 slab?
At 4 inches thick, a 10 ft by 10 ft slab is 1.23 cubic yards, or 1.36 cubic yards with a 10% allowance. At 6 inches it is 1.85 cubic yards before the allowance.
How many 80 lb bags make a cubic yard?
A cubic yard is 27 cubic feet. At 0.60 cubic feet per 80 lb bag that is 45 bags, and at 0.45 cubic feet per 60 lb bag it is 60 bags. Check the yield printed on your brand, then round up for the whole project.
How many square feet does one cubic yard of concrete cover?
Divide 324 by the thickness in inches. One cubic yard covers 81 square feet at 4 inches, 64.8 square feet at 5 inches, and 54 square feet at 6 inches, before any waste allowance.
How much does a cubic yard of concrete weigh?
Normal-weight concrete is roughly 145 to 150 pounds per cubic foot, so a cubic yard is close to 4,000 pounds. The calculator uses 150 pounds per cubic foot, which gives 4,050 pounds per cubic yard.
How much extra concrete should I order?
Ten percent is a common starting allowance for slabs. On a 4-inch slab it covers 0.4 inch of average extra depth. Uneven subgrade, trench-poured footings, and a long chute or pump line justify more.
What thickness should a concrete slab be?
The IRC sets a 3-1/2 inch minimum for slab-on-ground floors. Walks and patios are commonly poured at 4 inches, and driveways and garage floors are often 5 or 6 inches. The plans, the engineer, and local code decide.
Run the numbers for your job
Concrete Slab, Footing & Column CalculatorFree, runs in your browser, and uses the same formulas as the tables on this page.