BuildCalcENGINEERING
STRUCTURAL REINFORCEMENT · 0ms CLIENT MATH

Rebar Weight & Grid Spacing Calculator

Calculate linear footage, steel tonnage, bar counts, and ACI 318 tension lap splices for standard ASTM deformed reinforcing bars (#3 to #11).

Feet
Feet
Inches
Inches
Two-Way Grid (Mat)Reinforce in both directions
10%

Reinforcing Steel Schedule

Includes 10% contractor waste factor

Total Rebar Weight
573.1lbs
0.287 Tons (260 kg)
Linear Footage
858Linear Ft
261.5 Meters
Number of Bars
40Bars
20 lengthwise + 20 crosswise
Recommended Lap Splice
20" (approx. 1.7 ft)
40 × bar diameter tension lap
Unit Weight
0.668lbs/ft
Diameter: 0.5" (12.7 mm)
Nominal Area
0.2sq in
ASTM A615 Grade 60
0ms Client Math EngineStandard Dimensional Tolerances

Rebar Reinforcing Mat Layout

Size: #40.5" / 12.7mm)
Linear Footage858 ft
Total Weight573.1 lbs
Steel Tonnage0.287 Tons
ACI Lap Splice20" (approx. 1.7 ft)

ASTM A615 / A706 Specifications

BarDiameterWeight (lbs/ft)Weight (kg/m)Area (in²)
#30.375"0.3760.5600.11
#40.500"0.6680.9940.20
#50.625"1.0431.5520.31
#60.750"1.5022.2350.44
#70.875"2.0443.0420.60
#81.000"2.6703.9730.79
#91.128"3.4005.0601.00
#101.270"4.3036.4041.27
#111.410"5.3137.9071.56

Why bar count is floor(effective ÷ spacing) + 1

Why the +1 is not optional

Bars sit on-center. If you have 18 feet of effective width and 18-inch spacing, you do not have 18 ÷ 1.5 = 12 spaces and 12 bars. You have 12 spaces and 13 bars — one at each end plus the ones between. The formula is effective/spacing+1\lfloor \text{effective} / \text{spacing} \rfloor + 1. Dropping the +1 is how a 20-foot mat ships one bar short on every row.

Effective width is the slab or footing dimension minus cover on both edges. Cover is not decorative. ACI 318 and IRC tables set it so the bar has concrete around it. Weight is linear feet times the ASTM pounds-per-foot for that size. The ASTM table on the right already lists those unit weights; this guide does not reprint it.

The 40d lap shown here is a Grade 60 tension-lap approximation (40 × bar diameter). It is not the lap on your drawing. Class A/B, epoxy, lightweight concrete, and required development length change that number. Do not cut bars to 40d because this page printed it. Compression laps are often shorter; hook bars are a different takeoff entirely.

effective=overall2×edge cover\text{effective} = \text{overall} - 2 \times \text{edge cover}
bars=effectiveon-center+1\text{bars} = \left\lfloor \dfrac{\text{effective}}{\text{on-center}} \right\rfloor + 1
linear ft=bars×bar length\text{linear ft} = \text{bars} \times \text{bar length}
pounds=linear ft×lb/ft(ASTM A615)\text{pounds} = \text{linear ft} \times \text{lb/ft} \quad (\text{ASTM A615})
40d lap40×d(Grade 60 sketch)\text{40d lap} \approx 40 \times d \quad (\text{Grade 60 sketch})

Worked field example

22 × 18 foot mat, #5 at 18 inches on center, 3-inch edge clearance, two-way. Not the 20 × 20 / #4 / 12-inch default.

Effective length is 22 − 2 × 0.25 = 21.5 feet. Effective width is 18 − 0.5 = 17.5 feet. Spacing is 1.5 feet. Bars along the 22-foot side: floor(17.5 ÷ 1.5) + 1 = 12. Bars along the 18-foot side: floor(21.5 ÷ 1.5) + 1 = 15. Without the +1 you would have ordered 11 and 14 and left a gap at the far edge.

#5 weighs 1.043 lb/ft. Net steel is 12 × 21.5 + 15 × 17.5 = 520.5 feet, about 543 pounds before waste. A 40d lap on #5 is 25 inches — use it only as a reminder to look at the schedule, not as a cut list.

Cover and grade — what this page does not design

ASTM A615/A706 fix the bar you can buy. ACI 318 and IRC R506/R403 set cover and when a slab needs steel at all. This engine counts bars. It does not check temperature steel, shrinkage spacing, or whether welded-wire is allowed in place of the mat.

Cover and product — not a bar-size design

Provision
ACI 318 cover
Limit
Often 3 in to earth, 1.5 in to forms, 3/4 in in slabs (check the adopted edition)
Failure mode
Using 3-inch clearance in a formed wall that only needs 1.5
Provision
ASTM A615 / A706
Limit
Deformed bar grade and weldability
Failure mode
Ordering A615 where the spec wants A706 for welding
Provision
40d sketch
Limit
Grade 60 tension lap approximation only
Failure mode
Cutting laps from this page instead of the structural sheet

Where the field usually goes wrong

Omitting the +1 is the counting error. The other is treating welded-wire mesh as the same takeoff. WWM is ordered in rolls or sheets by square feet, not as #4 at 12 inches. Converting a W6×W6 sheet into “equivalent bars” and then running this calculator will not match the bundle the supplier sends.

Laps consume extra length that a simple grid count does not see unless you add them or raise the waste slider. A 20-foot stock bar in a 22-foot pour needs a splice; 40d is the reminder, not the cut. Mill lengths are 20, 40, and 60 feet — a 21.5-foot effective run is two 20s plus a lap, not one mythical 21.5-foot stick. Chairs and dobies are not in the pound total. Two-way versus one-way matters: uncheck the mat and you only get bars in one direction.

Frequently asked questions

Why add one after dividing by spacing?

On-center spacing counts gaps. floor(effective ÷ spacing) is the gaps; +1 is the bars at both ends.

Is 40d the lap on my drawing?

No. It is a Grade 60 sketch (40 × diameter). Class A/B, epoxy, and fy change it. Cut from the schedule.

Can I use this for welded-wire mesh?

No. Mesh is a sheet product. Order WWM by coverage, not as #4 equivalents.

Does edge clearance equal ACI cover?

It is the setback this page uses so the first bar is not on the form. Legal cover is the adopted table. Match the drawing.

One-way or two-way — which do I pick?

A slab mat is two-way. Bars only along a footing: uncheck the mat.

Where do the lb/ft numbers come from?

ASTM A615 nominal weights. The table to the right lists them. This guide does not copy it.

Does this replace the structural drawing?

No. Size, spacing, cover, and lap are design. This is a takeoff of a grid you already chose.